The programme was initially fast tracked however due to lack of resource from other contractor programmes it was re-adjusted to ensure the we could meet the milestone needs of the client and hand over key areas in a staged manner. As the project progressed, the client was occupying floors so Focus completed a high proportion of the works outside general working hours to minimise impact on the staff and students.