School admin block and 2 classroom blocks were leaking into the roof and wall cavities requiring:
New roof, wall framing and joinery
Roof iron
Internal lining and insulation
Complete redecoration and services.
SPECIAL FEATURES:
Install new reception and kitchen to the admin block
Library upgrade.
Whangaparaoa, Auckland
Duration:
58 weeks
Value:
$2.5M
CLIENT VISION DELIVERED:
Focus applied our knowledge of new school building codes to bring the buildings up to NZS standard 3604. The project was completed on time, on budget and with minimal disruption to staff and students.